top of page

Hydroelectric power plant Ovaro (UD)
Pelton 200 kW

Located in Ovaro (UD), with an installed power of 200 kW: construction and installation of the electro-mechanical works of the production workshop and the intake structure

Project year 2018

Location Ovaro (UD)

Waters

Description Vertical axis Pelton turbine 2 jets

Net head (m) 145

Flow rate (l/s) 160

Turbine power (kW) 200

 

Where we are

2 LOGO LUMIEI DEF_B_Drawing board 1.png

Via Comunità Carnica 7, 33029 Villa Santina UD

Tel: +39 0433 86075
Fax: +39 0433 866907

Lumiei Impianti Srl

  • Grey Facebook Icon
  • LinkedIn
  • Instagram

Lumiei fvg, Lumiei udine, Lumiei hydroelectric, Lumiei electromechanical, turbine plants friuli, Lumiei turbines, Lumiei plants,

Hydroelectric turbines Italy Lumiei plants

2 LOGO LUMIEI DEF_B_Drawing board 1.png

The characteristic of flowing water systems is the lack of an upstream storage basin and therefore the possibility of modulating the power based on the request. In fact, production follows the flow regime of the watercourse based on its seasonality. The construction of such hydraulic systems is advantageous because it has a low environmental impact and a low construction cost compared to basin systems, while maintaining excellent economic profitability.