Hydroelectric power plant Dimaro (TN)
Pelton 238 kW

Located in Dimaro (TN), with an installed power of 238 kW: construction and installation of the electro-mechanical works of the production workshop and the intake structure

Project year 2016

Location Dimaro (TN)

Waters

Description Vertical axis Pelton turbine 4 jets

Net head (m) 60

Flow rate (l/s) 450

Turbine power (kW) 238

 

Where we are

2 LOGO LUMIEI DEF_B_Drawing board 1.png

Via Comunità Carnica 7, 33029 Villa Santina UD

Tel: +39 0433 86075
Fax: +39 0433 866907

Lumiei Impianti Srl

  • Grey Facebook Icon
  • LinkedIn
  • Instagram

Lumiei fvg, Lumiei udine, Lumiei hydroelectric, Lumiei electromechanical, turbine plants friuli, Lumiei turbines, Lumiei plants,

Hydroelectric turbines Italy Lumiei plants

2 LOGO LUMIEI DEF_B_Drawing board 1.png
socialCard_Lumiei.png
Macchine rotative innovative per lo sviluppo e la gestione delle fonti rinnovabili

L’integrazione delle fonti rinnovabili (FER) richiede soluzioni per gestirne l'intermittenza così da garantire la stabilità della rete.

© 2024 all rights reserved Lumiei CF and PI 02361180306

Lumiei fvg, Lumiei udine,Lumiei idroelettrico,lumiei elettromeccanico,impianti turbine friuli,lumiei turbine,Lumiei impianti friuli,impianti idroelettrici su aquedotto

bottom of page